One tender my company worked on was for uninterruptible power supply (UPS) units. It needed delivery before the end of the federal fiscal year. The only supplier I found could deliver months later. We withdrew.
Since then, the buyer's year end has been part of my screen.
The federal fiscal year
The Treasury Board Secretariat says the Government of Canada's fiscal year begins on April 1 and ends on March 31 of the following calendar year.
The Financial Administration Act says the balance of an appropriation that is unspent at the end of a fiscal year lapses.
So money a department was given for one year doesn't automatically carry into the next. That's my reading of why some buyers set firm delivery dates before March 31. It's not an official rule that every purchase must arrive by then. Each tender sets its own dates.
Why it matters to a reseller
A tender posted in January with delivery "before March 31" leaves a few weeks. Your supplier's lead time has to fit, plus shipping, plus customs if it's imported.
If it doesn't fit, nothing else about the bid matters. You can't promise a date your supplier can't meet.
Add it to the screen
When I read a tender now, I check:
- The delivery date. Is it fixed, and is it near March 31?
- The supplier's lead time, in writing. From order to shipment.
- Shipping time to the delivery address. Plus customs if it's imported.
- The award date. Count from when the contract might arrive, not from today. Leave room for the gap between recommendation and contract.
If the total runs past the delivery date, the tender fails. That's question 4 of my supply gate, with the year end added.
If you already submitted
If you find out after submitting that the supplier can't meet the date, withdraw before closing. Withdrawing a submitted bid explains how. That's what we did.