Most of the tenders my company worked on, we chose not to submit. That sounds like failure. It isn't. Every bid we dropped at the right time saved us from a promise we couldn't keep, or a contract that would have lost money.
No-bid is a decision, and it deserves the same care as a bid.
Why we walked away
These are the real reasons, from our own tenders:
- No supplier price by our kill date. No firm written price, no bid.
- A partner fee not worth one bid. A publisher wanted a fee before it would let us resell. For a single tender, it didn't add up.
- Mandatory documents a publisher couldn't provide. If only the maker can produce a document the tender requires, and the maker says no, the bid is over.
- Documents behind a paid portal. Some local tenders put the documents behind a paid plan. We pay only when a bid is clearly worth it.
- Lead times past the buyer's dates. If the supplier can't deliver by the date in the tender, nothing else matters.
- Supply arrangement only. If only pre-qualified suppliers can bid, we can't. See three words that mean you can't bid.
Public Services and Procurement Canada (PSPC) lists questions to ask before you bid. The first is whether your business is capable of offering the product requested. Most of the reasons above come down to a "no" to that question.
Set a kill date on every live bid
A kill date is the day you stop if you still don't have what you need. I set one on every tender that passes my supply gate.
A simple way to pick it:
- Start from the closing date.
- Count back the days you need to price, write and submit once you have a supplier price.
- Add a day of slack.
- That's the kill date. Write it in the log next to the tender.
When the kill date passes and the thing I was waiting for hasn't come, I stop. I don't move the date because the tender still looks good. It always still looks good.
Before you submit, not after
The worst time to decide is after you've submitted. A submitted bid is a binding offer. If you submit hoping a supplier price will arrive later, you may have to withdraw on closing day, or deliver at a loss. Withdrawing a submitted bid covers how we learned that.
So the rule is simple. No firm supplier price, no submission.
Close out with the suppliers who helped
When a supplier has spent time on a quote for a tender you drop, send a short note. It keeps the door open for the next one.
Subject: [part number] quote, thank you
Hello [name],
Thank you for the quote on [part number]. We've decided not to go ahead with this one, so no order will follow.
I'll come back to you when a similar request comes up.
[name], [company]
Don't explain the tender, the buyer or the reason. Just close the loop.
What a no-bid still gives you
- Notes for next time. The same item often comes up again. Keep the supplier, the price and why you stopped.
- A clearer screen. If the same reason kills three tenders, add it to your kill rules. My daily screen lists ours.
Official sources
- Reference sheet: Preparing to bid on an opportunity (Public Services and Procurement Canada)
- Standing offers and supply arrangements (CanadaBuys)
Sources checked on .