When the tender wants an accessibility report and your software publisher doesn't have one

A federal software tender asked for an Accessibility Conformance Report (ACR). I asked several software publishers for one. None had one ready.

Accessibility Conformance Reports explains what an ACR is. This post is what to do when you can't get one, and what I did.

What the official guide says

Shared Services Canada's guide for including accessibility in ICT procurement says buyers are strongly encouraged to require all suppliers of ICT to submit an ACR.

When the report is due depends on what you're selling:

  • Off-the-shelf products. The guide says the original equipment manufacturer must provide the ACR with the bid.
  • Custom ICT. The ACR is provided as described in the contract.
  • An existing ACR against another standard. A new one can be due by a firm date set in the contract.

As a reseller, you don't write the ACR. The publisher does. So when the publisher has none, you have a problem only the publisher can fix.

First, read when the tender needs it

The guide says buyers write the requirement. So the tender decides. Before you chase anyone, find out:

  • Is the ACR mandatory? Or is it rated, or just requested?
  • When is it due? With the bid, or at or after award?
  • Against which standard? Canada's standard is CAN/ASC - EN 301 549:2024.

If it's mandatory with the bid and nobody has one, the bid can't pass. If it's due after award, there may be room.

Ask the buyer

If the tender isn't clear, ask the contracting authority in the question period. A short, exact question:

"Section [x] asks for an Accessibility Conformance Report. Is the report required at bid closing, or can it be provided after contract award?"

Asking the buyer a question covers how and when.

What we did

One publisher committed in writing to deliver an ACR within a set time after award. Another declined outright.

We checked whether the tender needed the ACR with the bid or at award. Then we bid with the publisher's written commitment, knowing it might not pass.

That was a risk we chose, not a recommendation. If the buyer had read it differently, or the publisher hadn't delivered on time, the bid or the contract could have failed.

If you go the same way

  • Get the commitment in writing. An email from the publisher with a delivery time, not a phone promise.
  • Check the standard. The commitment should name the standard the tender asks for.
  • Price the risk. If the report is late or falls short, what does it cost you? Could it cost you the contract?
  • Keep a backup. Is there another publisher whose product meets the requirement and has an ACR?

If you're starting out, do this next

  • In your next software tender, search for "accessibility" and "ACR" and note whether it's mandatory and when it's due.
  • Ask the publisher for its current ACR in your first email, with the quote request.
  • If no ACR exists, ask the publisher for a written delivery commitment.
  • If the tender is unclear, ask the contracting authority before the question deadline.