Margin by risk: why I don't use one markup for every bid

My default markup is 30% on landed cost. I don't use it on every bid. A bid with three firm supplier quotes and a bid with one shaky quote are not the same risk, so they shouldn't carry the same margin.

The default

My starting point: take the highest supplier quote, build the landed cost on it, and add 30%.

Two choices in that line matter.

  • The highest quote, not the lowest. If the cheapest supplier falls through, I may have to buy from the dearest one. My price has to survive that.
  • Worst-case landed cost. Highest quote and highest freight. The average hides the case that loses money. Landed cost lists every line.

When I go higher

  • Only one supplier price. If one supplier is the whole bid, I go much higher. If I win, the extra room lets me bring a second supplier on board, or absorb a price rise.

  • A supplier that won't hold its price. If a supplier can't hold the price for my offer period, or can't give a lead time, I raise the margin instead of chasing them for a promise they won't make. Other risks worth pricing in:

  • A short quote and a long offer. A quote valid for a week against an offer valid for 60 days is a risk. Prepay, credit applications and net terms explains the gap.

  • Foreign currency. A quote in US dollars, euros or pounds can move against you before you pay.

  • Several delivery points. Freight to two bases on two coasts costs more than freight to one, and is harder to quote.

  • Prepay. If I pay up front and wait to be paid, the money is tied up longer.

When I don't bid at all

No supplier reply, no bid. I never price a tender on a guess.

A worked example

Every number here is made up and round. It shows the steps, not a real bid.

Safe bid Risky bid
Supplier quotes Three, all firm One, valid 7 days
Highest quote $10,000 $10,000
Worst-case landed cost $11,500 $12,500 (dearer freight, currency room)
Markup 30% 50%
Bid price $14,950 $18,750

Same supplier price. Very different bid. The risky bid's price covers a dearer freight case, a currency swing, and room to find a second supplier.

The honest downside

On a lowest-price-compliant tender, the lowest compliant price wins. Reading an RFP explains the method. Every point of margin you add lowers your odds.

So a high margin on a risky bid often means you lose it. I accept that. Losing a risky bid costs me an evening. Winning one at a margin that can't absorb a problem can cost real money.

Before you set the margin, check what the government paid last time. How I check past contract prices shows how. If your safe price is already above the past range, more margin won't help.

If you're starting out, do this next

  • Pick a default markup and write it down.
  • For your next bid, build the landed cost on the highest quote and the worst-case freight.
  • Go through the risks above and note which apply.
  • Compare your final price with past contract prices before you submit.