My default markup is 30% on landed cost. I don't use it on every bid. A bid with three firm supplier quotes and a bid with one shaky quote are not the same risk, so they shouldn't carry the same margin.
The default
My starting point: take the highest supplier quote, build the landed cost on it, and add 30%.
Two choices in that line matter.
- The highest quote, not the lowest. If the cheapest supplier falls through, I may have to buy from the dearest one. My price has to survive that.
- Worst-case landed cost. Highest quote and highest freight. The average hides the case that loses money. Landed cost lists every line.
When I go higher
-
Only one supplier price. If one supplier is the whole bid, I go much higher. If I win, the extra room lets me bring a second supplier on board, or absorb a price rise.
-
A supplier that won't hold its price. If a supplier can't hold the price for my offer period, or can't give a lead time, I raise the margin instead of chasing them for a promise they won't make. Other risks worth pricing in:
-
A short quote and a long offer. A quote valid for a week against an offer valid for 60 days is a risk. Prepay, credit applications and net terms explains the gap.
-
Foreign currency. A quote in US dollars, euros or pounds can move against you before you pay.
-
Several delivery points. Freight to two bases on two coasts costs more than freight to one, and is harder to quote.
-
Prepay. If I pay up front and wait to be paid, the money is tied up longer.
When I don't bid at all
No supplier reply, no bid. I never price a tender on a guess.
A worked example
Every number here is made up and round. It shows the steps, not a real bid.
| Safe bid | Risky bid | |
|---|---|---|
| Supplier quotes | Three, all firm | One, valid 7 days |
| Highest quote | $10,000 | $10,000 |
| Worst-case landed cost | $11,500 | $12,500 (dearer freight, currency room) |
| Markup | 30% | 50% |
| Bid price | $14,950 | $18,750 |
Same supplier price. Very different bid. The risky bid's price covers a dearer freight case, a currency swing, and room to find a second supplier.
The honest downside
On a lowest-price-compliant tender, the lowest compliant price wins. Reading an RFP explains the method. Every point of margin you add lowers your odds.
So a high margin on a risky bid often means you lose it. I accept that. Losing a risky bid costs me an evening. Winning one at a margin that can't absorb a problem can cost real money.
Before you set the margin, check what the government paid last time. How I check past contract prices shows how. If your safe price is already above the past range, more margin won't help.