I was hunting for an obsolete part for a defence tender. A broker in the UK offered a different maker's part that it said was equivalent.
The price was about double the original maker's. That alone made it a loss on every unit. But price wasn't the only problem.
What the tender and my offer said
Two things stood in the way.
The tender. It named one part number and one maker's code. It said any other part number or maker code counted as an equivalent, and an equivalent needed the buyer's approval.
My own offer. I had already written in the offer that no equivalent or substitute was offered.
So taking the broker's part meant changing what I had promised, and asking the buyer to approve a different part. At double the price.
I stuck with the exact part. I kept the broker's alternative on file as a last-resort backup, nothing more.
What to check before you say yes
Before you accept a supplier's equivalent, read three things:
- The exact part rule. Does the tender name one part number, or a part number "or equivalent"? Reading an RFP explains the difference.
- The equivalent clause. If equivalents are allowed, what proof does the buyer want, and who approves it? When does approval happen: before closing, or after award?
- What you wrote in your offer. If you said "no equivalent offered", taking one changes your offer.
A bid that fails a mandatory requirement is out, however good the price. A part the buyer doesn't accept can fail the bid, or turn into a problem at delivery.
Compare on break-even, not on "it's available"
An available part isn't a good deal if you lose money on it. Work out your break-even unit cost: the most you can pay per unit and still not lose money at your bid price.
A made-up example, with invented round numbers:
- Your bid price is $100 a unit.
- Freight, duty, brokerage and other landed costs come to $15 a unit.
- Your break-even supplier price is $85 a unit.
If the exact part costs $45 and the "equivalent" costs $90, the equivalent loses $5 on every unit before you even ask whether the buyer will accept it. Landed cost shows how to build the $15.
When an equivalent is worth asking about
Sometimes it is the only way. If the exact part is gone everywhere, and the price works, an equivalent may be worth raising.
- Ask before closing, in the question period, through the contracting authority. Quote the clause and give the alternative's maker and part number.
- Get the evidence first. Datasheets for both parts, side by side, and any cross-reference from the original maker.
- Don't assume the answer. Until the buyer says yes in writing, plan on the exact part.
Reverse searching an NSN shows how to check whether a part from another maker is listed under the same stock number. That helps, but the tender's wording still decides.
Document it
Whatever you decide, write down:
- Who offered the alternative, the part number and the price.
- What the tender and your offer say about equivalents.
- Your break-even unit cost.
- What you decided and why.
If the exact part falls through later, you'll have your backup and your reasons in one place.